2022-2023
During the 2022-2023 fiscal year, some building upgrades will be made.
On Thursday, December 8, out of an abundance of caution, the Halifax Regional Centre for Education (HRCE) closed Bicentennial School after receiving test results indicating higher than acceptable levels of asbestos present in two of the three rooms under construction. The school remained closed on Monday, December 12 and Tuesday, December 13 while more testing was completed.
The school re-opened on Wednesday, December 14 after the HRCE received approval from the Nova Scotia Department of Labour, Skills, and Immigration along with clear test results from a third-party expert.
The following reports capture all relevant details:
1. 30128 – Bicentennial School – MicroVAC Report, December 8, 2022
2. 30128 – Report 02 – Bicentennial School – MicroVAC Report - REV, December 9, 2022
3. 30171 – Bicentennial School – Background Air Monitoring – Report 02, December 11, 2022
4. 30171 – Bicentennial School – MicroVAC Report, December 13, 2022
5. 319996 Occupancy and Dust Results Letter, 85 Victoria Rd, Dartmouth, NS, HRCE, 13Dec2022
Click here to view answers to your frequently asked questions.
Letters to Families
1. 30105 - Report 3 - Bicentennial School - Perimeter Air Monitoring, November 23, 2022
2. 30105 - Report 4 - Bicentennial School - Perimeter Air Monitoring, November 24, 2022
3. 30105 - Report 6 - Bicentennial School - FC Report, November 24, 2022
4. 30138 - Report 1 - Bicentennial School - Enclosure Pre-Inspection, December 1, 2022
5. 30138 - Report 2 - Bicentennial School - Perimeter Air Monitoring, December 2, 2022
6. 30138 - Report 3 - Bicentennial School - Post-Abatement Inspection, December 2, 2022
7. 30138 - Report 4 - Bicentennial School - FC Report, December 2, 2022
In June 2019, the Halifax Regional Centre for Education (HRCE) advised the school community funding had been secured to continue with upgrades to the building envelope (i.e. windows replacement and masonry repointing).
In May 2018, the Halifax Regional Centre for Education (HRCE) was advised it would again be receiving funds to complete upgrades to Bicentennial School. The funding will be used to continue upgrading the building envelope (i.e. windows replacement and masonry repointing).
In May 2017, the provincial Department of Education and Early Childhood Development informed the Halifax Regional School Board that additional funding would be provided to continue with renovations at Bicentennial School. The HRSB will use these funds to complete the roof replacement and continue installing windows.
On June 3, 2016, it was announced by the provincial Department of Education and Early Childhood Development, that additional funding would be provided to continue with renovations at Bicentennial School. The HRSB will use these funds to do some additional roofing work, replace a section of windows and undertake masonry repairs.
The provincial government announced a renovation project for Bicentennial School on May 14, 2015. The renovation included:
Paving nearing completion in August
October 13, 2015 - Roof work is progressing steadily. August 19, 2019 - Link (Update on project status to parents/guardians)