Bicentennial School Renovations

2022-2023

During the 2022-2023 fiscal year, some building upgrades will be made. 

Correspondence

  • August 30, 2023 - Link (Letter to families advising of project completion)
  • June 16, 2023 - Link (Letter to familiies with update on projects)
  • May 15, 2023 - Link (Letter to families with update on projects)
  • April 17, 2023 - Link (Letter to families with update on projects)
  • March 23, 2023 - Link (Letter to families with update on projects)
  • February 24, 2023 - Link (Letter to families with update on projects)
  • January 13, 2023 - Link (Letter to families with update on projects)
  • November 10, 2022 - Link (Letter to families with update on projects)
  • September 16, 2022 - Link (Letter to families with update on projects)
  • June 16, 2022 - Link (Letter to families advising of projects)

Asbestos Testing

On Thursday, December 8, out of an abundance of caution, the Halifax Regional Centre for Education (HRCE) closed Bicentennial School after receiving test results indicating higher than acceptable levels of asbestos present in two of the three rooms under construction. The school remained closed on Monday, December 12 and Tuesday, December 13 while more testing was completed.

The school re-opened on Wednesday, December 14 after the HRCE received approval from the Nova Scotia Department of Labour, Skills, and Immigration along with clear test results from a third-party expert.

The following reports capture all relevant details:

1. 30128 – Bicentennial School – MicroVAC Report, December 8, 2022 
2. 30128 – Report 02 – Bicentennial School – MicroVAC Report - REV, December 9, 2022 
3. 30171 – Bicentennial School – Background Air Monitoring – Report 02, December 11, 2022 
4. 30171 – Bicentennial School – MicroVAC Report, December 13, 2022 
5. 
319996 Occupancy and Dust Results Letter, 85 Victoria Rd, Dartmouth, NS, HRCE, 13Dec2022

Click here to view answers to your frequently asked questions.

Letters to Families

  • December 13, 2022 - Link (Letter to families advising of test results)
  • December 13, 2022 - Link (Letter to families advising of school reopening)
  • December 12, 2022 - Link (Update to families on school closure)
  • December 11, 2022 - Link (Update to families on school closure)
  • December 8, 2022 - Link (Letter to families advising of school closure)

Additional Information

1. 30105 - Report 3 - Bicentennial School - Perimeter Air Monitoring, November 23, 2022
2. 
30105 - Report 4 - Bicentennial School - Perimeter Air Monitoring, November 24, 2022
3. 30105 - Report 6 - Bicentennial School - FC Report, November 24, 2022
4. 30138 - Report 1 - Bicentennial School - Enclosure Pre-Inspection, December 1, 2022
5. 30138 - Report 2 - Bicentennial School - Perimeter Air Monitoring, December 2, 2022
6. 30138 - Report 3 - Bicentennial School - Post-Abatement Inspection, December 2, 2022
7. 30138 - Report 4 - Bicentennial School - FC Report, December 2, 2022

2019-2020

In June 2019, the Halifax Regional Centre for Education (HRCE) advised the school community funding had been secured to continue with upgrades to the building envelope (i.e. windows replacement and masonry repointing).

Correspondence

  • August 21, 2019 - Link (Update on project status to parents/guardians)
  • June 25, 2019 - Link (Project update)
  • June 6, 2019 - Link (Letter to parents/guardians advising of funding for the project)

2018-2019

In May 2018, the Halifax Regional Centre for Education (HRCE) was advised it would again be receiving funds to complete upgrades to Bicentennial School. The funding will be used to continue upgrading the building envelope (i.e. windows replacement and masonry repointing).

Correspondence

  • December 11, 2018 - Link (Expansion of renovation project)
  • November 6, 2018 - Link (Update on progress of renovations)
  • May 24, 2018 - link (Letter to parents/guardians advising of funding for the project)

2017-2018

In May 2017, the provincial Department of Education and Early Childhood Development informed the Halifax Regional School Board that additional funding would be provided to continue with renovations at Bicentennial School. The HRSB will use these funds to complete the roof replacement and continue installing windows.

Correspondence

  • November 14, 2017 - link (Project update from Superintendent)
  • June 14, 2017 - link (Letter from Superintendent informing community of additional funding)

2016-2017

On June 3, 2016, it was announced by the provincial Department of Education and Early Childhood Development, that additional funding would be provided to continue with renovations at Bicentennial School. The HRSB will use these funds to do some additional roofing work, replace a section of windows and undertake masonry repairs.

Correspondence

  • November 22, 2016 - link (Project update from Superintendent)
  • September 12, 2016 - link (Project update from Superintendent)
  • June 14, 2016 - link (Letter from Superintendent announcing project)

2015-2016

The provincial government announced a renovation project for Bicentennial School on May 14, 2015. The renovation included:

  • Replacing part of the roof;
  • Replacing some windows and wall cladding; and
  • Reconfiguring how students come and go through the main entrance.

Correspondence

  • April 11, 2016 - link (Project update from Superintendent)
  • December 15, 2015 - link
  • September 2, 2015 - link
  • May 14, 2015 - link

Pictures

Paving nearing completion in August

October 13, 2015 - Roof work is progressing steadily. August 19, 2019 - Link (Update on project status to parents/guardians)